CLIENT:- SUNCOR (Calgary Canada)
https://www.suncor.com/
Date: – 2018 – 2019
- Tailings Portfolio-Tailing Mining Project’s FEED Class 3 Estimate ($50M- $100M)
- Fort hills Concept select Class 5 Estimate’s ($20M- $200M)
- Quantity take-off, pricing, and laboring for the civil, piping, instrumentation & mechanical equipment accounts and reporting of the costs to the Lead Estimator and Project Manager Providing control estimates to owner companies for the purpose of financing and to enable the creation of the WBS & budget for developing projects.
- Doing analysis, technical trouble shooting & problem solving in Kbase, ICE, Access & other. front end cost study tools.
- Evaluation of sub-contractor bit-tabs, conducting cost comparison using control estimate and subcontractor’s estimate.
- Preparing formal estimate presentations, reports for internal executive management and external client review.
- Field visit, collection of data, field survey; Calculate MTO from drawings, read & understand drawings & specification